Do I need planning permission for a rear extension?

A single-storey rear extension doesn't usually need planning permission if it's no more than 3m deep on a semi-detached or terraced house (4m on a detached house) and no more than 4m tall. With prior approval you can go up to 6m or 8m. Flats, listed buildings and some protected areas have stricter rules.

What size rear extension can I build without planning permission?

What are the permitted development rules for rear extensions?

To be permitted development, a rear extension must meet every one of these:

Bigger projects can still be permitted development after prior approval:

What counts as the original house?

All the depth limits are measured from the back wall of the original house: the house as it was first built, or as it stood on 1 July 1948 if it's older. If a previous owner added a conservatory or kitchen extension, that counts towards the limit. So if your semi already has a 2m extension, a new one joining onto it can only add another 1m under the standard limit.

Heights are measured from the ground next to the extension. On a sloping garden, use the highest ground level next to it.

Can I build a 6m or 8m extension without planning permission?

If you want to go beyond 3m (semi or terrace) or 4m (detached), you can apply for prior approval for a single-storey extension of up to 6m or 8m. It's a lighter process than a planning application:

  1. You send the council a description of the extension, its depth, its height and eaves height, and a plan.
  2. The council writes to the neighbours whose land adjoins yours, including at the back. They have 21 days to object.
  3. If no neighbour objects, the council doesn't assess the effect on them, and the extension can go ahead as long as it meets the other limits. If a neighbour does object, the council decides whether the extension would harm their living conditions, such as their light, outlook or privacy.
  4. The council has 42 days to decide. If it doesn't tell you in that time, you can go ahead.

The larger scheme isn't available in conservation areas, National Landscapes, national parks, World Heritage Sites or Sites of Special Scientific Interest.

Do two-storey extensions need planning permission?

A two-storey extension is permitted development if it extends no more than 3m beyond the original back wall and leaves at least 7m to the rear boundary. The roof pitch should match the house as far as practicable, and any upper-floor windows in the side walls must be obscure-glazed and fixed shut below 1.7m above the floor. Two-storey extensions aren't permitted development in conservation areas, National Landscapes, national parks or World Heritage Sites.

When does a rear extension need planning permission?

Check your own address: put a pin on your house and we'll look up the conservation areas, listed buildings, Article 4 directions and other designations there.

Check my rear extension

Where are the rules stricter?

Do I need building regulations approval?

Planning permission and building regulations are separate. Planning is about whether you can build it and how it looks; building regulations are about whether it is built safely (structure, fire safety, insulation, drainage). Permitted development only covers planning, so you may still need building regulations approval.

Rear extensions almost always need building regulations approval, covering foundations, structure, insulation, drainage and fire escape. Building over or near a public sewer also needs your water company's agreement.

How can I prove I don't need planning permission?

If you're confident your project is permitted development, you can apply to your council for a Lawful Development Certificate. It's a formal confirmation that the work is lawful without planning permission, it costs less than a planning application, and it's useful when you come to sell the house. If you're not sure, many councils offer pre-application advice.

Last reviewed Based on General Permitted Development Order 2015, Schedule 2, Part 1, Class A